Incorrect billing dispute MAXIMeyes

Gas and Elec Connections, Harrow Central Mosque

Project: Provision of new gas and electricity connections (including metering) for Harrow Central Mosque development

Client: Harrow Central Mosque and Masood Islamic Centre

Project Value: Over £7.5 million

Harrow-Mosque

Details: New site requiring gas connection with a total load of 600kw/hr and 3 electrical connections totalling 386KVA.

Action Taken: MAXIMeyes scrutinised the initial design, and consequent discussions with the M&E consultant on site allowed us to reduce the electrical load from 386KVA to 250KVA. This eliminated the requirement for an on-¬site HV substation which could not be accommodated due to structural design. By liaising with the local DNO and the appointed solicitor, we were in a position to obtain the wayleaves much faster.

Net Benefit:

  • Cost reduction of £50,000 by avoiding the installation of an on-¬site HV substation.
  • Completion time reduced from 5 to 3 months.
  • Provision of metering and competitive supply contracts.